This procedure records the completion dates for the entire project.
Procedure
-
Expand the project, if necessary, to display its items.
-
Right-click the Default Milestones item, and select Manage from the menu.
The Manage Milestones dialog appears.
-
Right-click the milestone whose completion dates you want to record, and select Set finished date... from the menu.
An interactive calendar appears.
-
Select the required date, then click OK.
You'll return to the Manage Milestones dialog where the modified date will be displayed.
-
Click OK when you're finished.