Record map-specific milestone completion dates

This procedure records the completion dates of a specific deliverable within a project.

About this task

Procedure

  1. Expand the project, if necessary, to display its items.
  2. Expand the Deliverables item.
    The deliverable maps appear.
  3. Expand the map whose milestone completion dates you want to record.
  4. Right-click the Milestones item, and select Manage from the menu.
    The Manage Milestones dialog appears.
  5. Right-click the milestone whose completion dates you want to record, and select Set finished date... from the menu.
    An interactive calendar appears.

    Assignment calendar
  6. Select the required date, then click OK.
    You'll return to the Manage Milestones dialog where the modified date will be displayed.
  7. Click OK when you're finished.