This procedure records the completion dates of a specific deliverable within a project.
Procedure
-
Expand the project, if necessary, to display its items.
-
Expand the Deliverables item.
The deliverable maps appear.
-
Expand the map whose milestone completion dates you want to record.
-
Right-click the Milestones item, and select Manage from the menu.
The Manage Milestones dialog appears.
-
Right-click the milestone whose completion dates you want to record, and select Set finished date... from the menu.
An interactive calendar appears.
-
Select the required date, then click OK.
You'll return to the Manage Milestones dialog where the modified date will be displayed.
-
Click OK when you're finished.